Customization: | Available |
---|---|
After-sales Service: | Online |
Warranty: | 1 Year |
Still deciding? Get samples of US$ 3000/Piece
Request Sample
|
Suppliers with verified business licenses
Audited by an independent third-party inspection agency
Main performance indicators
Model |
YL-PDT |
Main Control Unit |
Low power consumption embedded industrial computer |
Display screen |
8.4 inches true color LCD display (highlighted)800×600 |
Storage capacity |
8G |
Power supply mode |
Built-in high performance rechargeable lithium battery which can provide at least 6h power |
Operating method |
Touch screen |
Sampling interval |
5μs~65535μs |
Record length |
1024 point |
Sampling resolution |
24 bit AD |
The signal bandwidth |
1Hz~12kHz |
Floating point amplifier |
1 ~ 256 times (automatic adjustment of instrument according to signal size) |
System noise |
<20μv |
Dynamic range |
≥ 100dB |
Mode for transferring data |
USB |
Channel number |
5 channels(2 channel acceleration +2 channel strain ,1 Low strain channel) |
Sensor |
Speedometer, front IC piezoelectric accelerometer, strain ring |
Working temperature |
-20ºC~+55ºC |
Volume |
266×80×50 mm |
Weight |
1.9 kg |
Pile Test Analyzer Pile High Strain Tester Pile PIT Test Intetrity Analyzer Pile Driving Analyzer
Instrument information area
The instrument information area is mainly used to display the remaining battery percentage, the system time, the project of current operation and the file name of single pile.
At the same time, the button of screen brightness adjustment is provided, you can adjust the screen brightness in real time according to the scene environment.
The instrument information area will be displayed in each following operation interface.Project information setting area
Project information setting area
Click [Project] after entering in the setting interface, the project information setting is as shown in Figure 2-2.
1 Project name
Create a new project and input the name of the construction site and save the pile files under the folder of this new project.
2 Inspector ,Testing firm
Input the information of testing staff and testing firm on site.
3 Pile No. (Pile number)
Input the pile No. in test and the file name of the pile will be the default when saved.
4 Sys-time (System time)
If the current system time of the instrument is not accurate, you can correct the system time in this.
5 T-PL (Total pile length),M-PL (Length of pile under measuring point),D-PL (length of driven pile ) .
Refers to the total pile length from the top to the bottom of the pile, the pile length from the sensor to the bottom of the pile, and the pile length buried part of the pile respectively.
6 DIA (Diameter )
Refer to the diameter of the pile.
7 WV (the wave velocity of the pile) The average wave velocity of the pile.
8 M-WV (the wave velocity of the measuring point)
Refers to the wave velocity of the pile measuring point where the sensor is installed.
The wave velocity of ordinary steel pile is 5210m/s, while the wave velocity of concrete pile ranges 3000 ~ 4500m/s.
9 SA(sectional area of the pile),M-SA(sectional area of the measuring point),B-SA( sectional area of the bottom pile )
It refers to the average sectional area of the pile, the sectional area at the sensor installation point and the sectional area at the bottom of the pile respectively.
10 ρ (the density of the pile) ,M-ρ (the density of the measuring point)
Refer to the average density of the pile and the density at the sensor installation point.
The Density Of General Pile Material
Steel pile |
Precast concrete pile |
Centrifugal pipe pile |
Bored concrete pile |
7850kg/m3 |
2450~2500kg/m3 |
2550~2600kg/m3 |
2400kg/m3 |
11 Eigenvalue (the eigenvalue of foundation pile)
Refers to the characteristic value in the design drawing of the pile.
12 SF(Safety factor)
The designed safety factor of the pile
13 HW (hammer weight)
The weight of drop hammer.
14 Drop Height
The height of drop hammer.
15 Hammer Type
There is free drop hammer, diesel hammer, air hammer, and some other options.
16 Consider Inertia
There is two option, Yes and No.